Release agents and process chemical specialties
Published

Composite submarine camels win with long-term durability

U.S. Navy wisely opts for more expensive submarine moorings that maximize lifecycle cost efficiency.

Share

This story begins with an unlikely premise: the U.S. Navy needed to solve a problem, and it was willing to spend more money up front on a solution if that solution promised net savings in the long run. The problem? Poor durability of its deep-draft submarine camels. These large and mostly submerged metal or wood structures are attached to a mooring structure and fitted with rubber bumpers to provide a buffer between the Navy’s submarines and the waterfront where they are berthed. The camel deflects or compresses with vessel movement and prevents damage to the hull, diving planes, screws, fairings, special skin treatments and other equipment by absorbing the sub’s energy — which is considerable, given the 560-ft/171m length and 17,000 tons of water displaced by berthed vessels, including the Ohio class submarine, the heaviest in the fleet.

Given the saltwater environment in which they work, metal and wood camels require removal every two years for inspection and repair, which can be substantial if corrosion has begun. The other challenge the Navy faced was that it had 17 unique camel designs in ports around the world. Each camel was designed to accommodate a specific submarine type, which, in addition to the Ohio, includes the Los Angeles, Virginia and Seawolf classes.

Design and engineering firm Whitman, Requardt & Assoc. (WR&A, Baltimore, Md.) and composites manufacturer Composite Advantage (CA, Dayton, Ohio) were tasked with developing a universal composite camel that would meet that challenge and accommodate any U.S. Navy sub type, anywhere in the world.

The Navy’s criteria for the new camel included not only the ability to absorb the energy generated by a berthing submarine, but also the freeboard (how much of the camel would sit above the waterline), the list and trim angles, and the overall flotation stability requirements. The Navy’s request for proposal (RFP) specified that the level floating position of the camel must be maintained within a 1-inch/25.4-mm tolerance side to side and front to back. Further, the freeboard must be maintained within a 1-ft/0.3m tolerance.

“We were dealing with a unique shape and the criteria were somewhat at odds with each other in that if we designed to meet one requirement, issues surfaced with the other criteria.”

The RFP also stipulated that the camels must meet performance requirements in three load scenarios: berthing of a submarine, mooring of a submarine and lowering and lifting the camel into and out of the water. Berthing assumes a submarine velocity of 0.4 ft/sec (0.12 m/sec), which is approximately 200 ft-kip of energy. Mooring loads — caused by waves, wind and other forces — are, by comparison, smaller than berthing forces. The load path for berthing and mooring are horizontal, but the load path for lowering and lifting the camel into and out of the water is vertical; discrete lifting points on the camel, therefore, would be required and would have to withstand an anticipated mass in excess of 45 metric tonnes (100,000 lb).

“We were dealing with a unique shape and the criteria were somewhat at odds with each other in that if we designed to meet one requirement, issues surfaced with the other criteria,” says Matthew Lambros, structural engineer for WR&A. “This was largely due to the fact that a number of properties affecting the camel, such as volumes and densities, can vary and must be considered to establish precise flotation calculations.”

Working with CA, WR&A developed a design that comprises five composite structures, or modules, that are assembled on site to build the 25 ft by 9 ft by 11.5 ft (7.6m by 2.7m by 3.5m) camel. CA president Scott Reeve says the two largest modules, the upper and lower main boxes, are stacked (see photos). Two others, called wing walls, are installed on each side of the stack, and a third module is front mounted to provide the surface that faces the submarine. Attached to this front surface are the rubber fenders that contact the submarine. On the backside of the camel, a series of ultrahigh molecular weight polyethylene rubbing strips provide a contact surface where the camel meets the fixed dock structure.

The modules are made by assembling and bonding composite panels. Most panels have a sandwich construction, featuring 3.5-inch/89-mm thick TYCOR foam core (Milliken & Co., Spartanburg, S.C.) faced and edged with 0.3-inch/7.62-mm thick layers of uniaxial and triaxial glass fiber fabric from V2 Composites (Auburn, Ala.). This structure is hand layed, vacuum bagged and infused with Hetron 992 or Derakane 610 vinyl ester resin, supplied by Ashland Performance Materials (Dublin, Ohio). The foam core incorporates fiberglass shear webs, spaced at 1.5 inch/38.1 mm intervals. Where the panels are subjected to biaxial bending or significant shear forces, a bidirectional core is used. This consists of unidirectional core that is cut into short lengths (perpendicular to the shear webs) and wrapped in additional fiberglass fabric, thus providing shear webs in both directions.

Reeve says some of the camel’s primary contact points — those that see the most physical and mechanical stress — are designed for impact resistance as 1.5-inch/38.1-mm thick solid laminates. Each module and, later, the entire camel structure, is bonded together with an adhesive provided by SCIGRIP (Durham, N.C.).

The goal was to put the camel’s center of gravity as far as possible below the waterline to maintain rotational stability — easier said than done.

Structural analysis of the camel included a 3-D finite element analysis (FEA) of the entire structure, using RISA-3D FEA modeling software developed by RISA Technologies (Foothill Ranch, Calif.). The model consisted primarily of a series of meshed plate elements; the material and section properties of the plate elements were input manually to match the properties of the composite sandwich panels. Berthing, mooring and lifting (gravity) loads were applied to the model, and the resulting forces were used for panel and connection design. The submarine berthing energy absorbed by the marine fenders was converted to a force using charts and tables provided by marine fender manufacturers. The contact points from the camel to the mooring structure were modeled using compression-only lateral supports.

The panel properties were determined through an extensive testing program developed specifically for the camel design. For each failure mechanism identified in the structural analysis, the panel properties from the testing program were compared to the results of the analysis to determine the factor of safety against failure. Reeve says the calculated factors of safety were discussed with the owner, engineer and fabricator to ensure there was a consensus regarding their acceptability. Where possible, the safety factors also were compared to industry standards. For safety factors that were determined to be insufficient, changes to the design or fabrication methods were made as required.

 

Fabricating for flotation

After the camel’s design was finalized and manufacturing began, Reeve says another challenge presented itself: buoyancy management. Almost all of a camel rests below waterline, but the composite camels are inherently too buoyant for the application. The goal, then, was to put the camel’s center of gravity as far as possible below the waterline to maintain rotational stability — easier said than done.

Reeve says calculating the center of buoyancy and center of gravity included the tedious process of determining the relative position and density of each camel component, including panels, flotation foam, marine fenders and connection angles and hardware. Increasing the ballast weight to achieve the required freeboard, for example, would impact the angle of flotation. The final solution had to achieve a balance among all the design criteria.

Ultimately, says Reeve, CA determined that ballast must be added to submerge the camel and keep it trim against the submarine. This is done in three ways. First, after the 70,000-lb/31,751-kg camel is assembled, 35,000 lb/15,876 kg of concrete is poured into the center box. Second, a series of movable steel plates are installed over the ballast; they are adjusted from side to side in the box after the camel is floated for the first time to bring the entire structure trim. Third, holes are drilled in the box sides to allow them to fill with water. “The water helps keep the structure stabilized,” says Reeve. “It doesn’t bob or move as much.”

CA’s first camel was assembled on site at Naval Submarine Base New London (Groton, Conn.) in October 2010 and installed a month later for a flotation test. Since then, the Navy has installed two more camels, and CA is now manufacturing another for Naval Station Norfolk (Norfolk, Va.). “Feedback from Navy facilities engineers and port operations is very favorable,” says CA vice president Andy Loff. “Elimination of recurring maintenance is a major operational benefit, and multiple bases are now looking at the composite camels for future use.”

Reeve says the Navy is installing about two composite camels per year and is looking at other camel-like applications for the material, despite the fact that the CA camels cost 40 to 50 percent more than the old metal and wood versions. He lauds the unusual foresight: “The Navy basically said, ‘I’d much rather pay a little more up front than pay a lot more over a 10-year period.’” And with camels now expected to last 25 years or longer, the savings will live on. Mission accomplished.

Composites One
Wickert Hydraulic Presses
Compression Molding
Park Aerospace Corp.
Release agents and process chemical specialties
Ad showing Janicki CNC Mill machining part in tool
NewStar Adhesives - Nautical Adhesives
Airtech

Related Content

Composite resins price change report

CW’s running summary of resin price change announcements from major material suppliers that serve the composites manufacturing industry.

Read More

Henkel releases digital tool for end-to-end product transparency

Quick and comprehensive carbon footprint reporting for about 58,000 of Henkel’s adhesives, sealants and functional coatings has been certified by TÜV Rheinland.

Read More
Adhesives

Belzona composite wrap restores corroded carbon steel pipeline

Two-part epoxy paste, epoxy structural adhesive, composite wrap and anti-corrosion coating prevent environmental and economic loss for customer.

Read More

XlynX Materials BondLynx and PlastiLynx for low surface energy PP, PE substrates

Award-winning Xlynx materials use breakthrough “diazirine” technology to boost bond strength up to 950% as adhesives, primers and textile strengtheners.

Read More

Read Next

Application

CFRP planing head: 50% less mass, 1.5 times faster rotation

Novel, modular design minimizes weight for high-precision cutting tools with faster production speeds.  

Read More
Aerospace

Plant tour: A&P, Cincinnati, OH

A&P has made a name for itself as a braider, but the depth and breadth of its technical aptitude comes into sharp focus with a peek behind usually closed doors.

Read More
RTM

VIDEO: High-rate composites production for aerospace

Westlake Epoxy’s process on display at CAMX 2024 reduces cycle time from hours to just 15 minutes.

Read More
Release agents and process chemical specialties