Airtech
Published

FRP forms enable fluted concrete column design

 The Century Project, a 42-story luxury condominium tower in Los Angeles, Calif. , designed by Robert A. M.

Share

 The Century Project, a 42-story luxury condominium tower in Los Angeles, Calif., designed by Robert A.M. Stern Architects (New York, N.Y.) and under construction since June 2007, required top-notch construction techniques and refined detailing. For the 200 fluted concrete columns that support the balconies on the nearly 1 million ft² (92,900m²) elliptically-shaped building's upper floors, the project's architectural firm-of-record, HKS Inc. (Dallas, Texas), enlisted the help of the project's concrete contractor, Webcor Concrete (San Mateo, Calif.). Although Webcor considered steel and plastic concepts for the formwork, a composite solution from Molded Fiber Glass Construction Products (MFG-CP, Independence, Kan.) was judged to be the best approach. MFG-CP produced 15 custom fluted column forms and many standard round column forms, says MFG-CP's sales and marketing manager, Joe Kusiak.

According to Kusiak, forms had to provide sufficient flexural strength to support the typical 13-ft long, 3-ft diameter (4m long, 1m diameter) poured concrete sections and had to strip or release easily from the concrete to ensure a "lavishly smooth" surface finish to meet the project's aesthetics. To achieve these goals, MFG-CP's designers developed a four-piece form — that is, each piece forms one-quarter of the column circumference — with raised flanges along each seam for joining. The forms were hand layed in shaped fiberglass cavity molds. After application of a Frekote mold release, supplied by Henkel Corp. (Rocky Hill, Conn.,), the mold surface was gel coated. The next step was to apply 24-oz/yd² woven E-glass roving from Owens Corning Composite Materials LLC (Toledo, Ohio) followed by a "core" layer of 3-oz/yd² chopped strand mat, and then another ply of woven roving. The layup was wet out with general-purpose polyester resin supplied by AOC Resins (Collierville, Tenn.). "The mold included details to create the integral joining flanges," notes Kusiak.

On the job site, a chemically reactive release agent is applied to the inside of the form, and, after installation of the rebar and base, approximately 3 yd³ of concrete are poured into the form in about three minutes. Metal "coil bolts" with large threads hold the form segments together. After a day or two, the forms are "stripped" off, easily accomplished thanks to the four-piece design, and reused. The project's architect, Patrick Treadway, says, "The fluted concrete columns were more cost-effective than the originally conceived precast or stone options and have saved construction time."

Related Content

industrial CNC routers
Smart Tooling
Airtech
Harper International Carbon Fiber
3D industrial laser projection
CAMX 2024
Airtech
CompositesWorld
Airtech International Inc.